Project

Hume Freeway Continuous Road Safety Barriers – Detailed Design

Safe System Solutions Pty Ltd was engaged by Regional Roads Victoria to provide project management, design and technical advice services for the installation of continuous safety barriers on over 60km of divided carriageway roads, including the Hume Freeway, Western Port Highway and South Gippsland Highway.

Services included: (1) Agreeing project standards, scope and timeframes; (2) site investigations; (3) design of either flexible w-beam guardrail or wire rope barriers for roads with 100km/h and 80km/h speed limits passing through builtup and rural areas; (4) ongoing design and technical advice during construction.

Project: Hume Freeway Continuous Road Safety Barriers - Detailed Design
Client: Regional Roads Victoria / VicRoads / Department of Transport (Vic)
Year: Feb 2019 – Feb 2020
Key Staff:

Jamie Robertson | Reece Gunther